What must the operator, signalman, and crew attend before hoisting a personnel platform?

Prepare for the Term 8 Crane Signals Test with our interactive quiz. Study using multiple choice questions and learn effective crane operation signals effortlessly. Enhance your knowledge and get ready to excel!

Before hoisting a personnel platform, it is crucial for the operator, signalman, and crew to attend a pre-lift meeting. This meeting allows the team to discuss the specific details of the lift, including the lifting plan, roles and responsibilities, site conditions, and any potential hazards. Ensuring that everyone is on the same page will minimize risks during the operation and improve communication among the crew members.

A pre-lift meeting serves as an essential element in maintaining safety and efficiency during the hoisting process and is required by safety regulations. It prepares everyone involved for the operation by confirming that all necessary precautions are understood and that any questions or concerns can be addressed beforehand.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy